News Flash Home
The original item was published from 7/15/2020 9:28:10 AM to 10/1/2020 12:00:08 AM.

News Flash

Public Works/Road Work

Posted on: July 15, 2020

[ARCHIVED] Sanitary Sewer Improvement Project – Pheasant Run

Road work ahead

July 15, 2020

FOR IMMEDIATE RELEASE


For more information contact: Engineering Department, 269-966-3343

Sanitary Sewer Improvement Project – Pheasant Run

BATTLE CREEK, Mich. — A city contractor will begin working on the Pheasant Run cul-de-sac sanitary sewer tomorrow.

This project involves replacement of 642 feet of sanitary sewer. Normal work hours will be from 7 a.m. to 6 p.m., dependent on the weather and any unforeseen circumstances.

This work is estimated to take approximately two months.

Access will be maintained to local traffic and driveways in the area of the cul-de-sac. Limited delays may be experienced during this work.

Please use caution driving through these areas.  We appreciate everyone’s patience during these work times.


###