[ARCHIVED] Chip seal/ ASFALTADO

Road work ahead

July 14, 2020

FOR IMMEDIATE RELEASE

For more information contact: Engineering Division, 269-966-3343 

Chip seal/ ASFALTADO

BATTLE CREEK, Mich. — Pavement Maintenance Systems will begin applying chip seal treatments to various city streets tomorrow, Wednesday, July 15.

The following streets will be chip sealed, with work taking place from approximately 6 a.m. to 7 p.m.  Work is expected to finish by July 29, weather permitting. 

Riverside Drive - Beckley Road to Columbia Avenue

Upton Avenue - Kendall Street to Angell Street

Union Avenue - Michigan Avenue to Van Buren Street

Roosevelt Avenue - Goodale Avenue to Garrison Avenue

Chip seal is an effective way to extend the life of street pavement, lasting five to six years. Crews apply liquid asphalt and small stone chips, then roll over it. 

The streets will remain open and neighbors will have access to their properties.  Traffic regulators will be in place maintaining one-way traffic.  Please plan for intermittent traffic disruptions, which could cause delays.  

Motorist are advised to seek alternate routes. 

Please do not park on these streets during work hours; vehicles will be towed.   

Residents on these streets will receive door hangers the day before work begins.

We appreciate everyone’s patience during this and all work to maintain our infrastructure.

En Español 

Se realizará el sellado superficial con gravilla y asfalto en las siguientes calles, y los trabajos tendrán lugar aproximadamente en el horario de 6 a.m. a 7 p.m. del día 29 de julio. La realización de este trabajo depende del clima. 

Riverside - Beckley a Columbia 

Upton - Kendall a Angell 

Union - Michigan a Van Buren 

Roosevelt - Goodale a Garrison 

El sellado superficial con gravilla y asfalto es una forma efectiva de extender la vida útil del pavimento de la calle, hasta una duración de cinco a seis años. Para este sellado, los equipos vierten asfalto líquido y gravilla sobre el pavimento, y luego lo apisonan. Sobre este se vierte emulsión asfáltica y una nueva capa de asfalto.

Las calles permanecerán abiertas y los vecinos tendrán acceso a sus propiedades. Tenga en cuenta que puede haber interrupciones intermitentes en el tráfico. No estacione en estas calles durante el horario del trabajo; se remolcarán los vehículos que lo hagan.


###